This contract encompasses an extensive eight-phase project involving the demolition, renovation, and addition to Atikokan High School in Atikokan, Ontario.
A key challenge of the project is maintaining a fully operational and occupied school environment throughout construction, requiring precise planning, stringent safety measures, and seamless communication.
Finn Way General Contractor assumed the role of general contractor, managing the comprehensive retrofit of the existing one-story school building and constructing two new school wings.
The project’s success hinges on a phased construction approach, which was designed to minimize disruption and prioritize safety. The detailed phases are as follows:
Phase 1: Preparatory work to support the commencement of Phases 2 and 3.
Phase 2: Construction of the new EarlyON Childcare and Family Center, along with associated site work to create a dedicated and functional space for early childhood programs.
Phase 3: Construction of the new east and west wing additions, along with the renovation of the existing north and south wings, providing expanded learning spaces and improved infrastructure.
Phase 4: Renovation of the multi-use shop area, upgrading the facilities to better accommodate technical and vocational programs.
Phase 5: Renovation of Grayson Hall, enhancing its functionality and aesthetic appeal for school and community events.
Phase 6: Renovation of the small gymnasium, paired with an additional buildout to improve the school’s athletic facilities.
Phase 7: Renovation of the shop wing and library wing, modernizing these critical learning spaces for current and future needs.
Phase 8: Final phase involving the demolition of the remaining portions of the existing school facility. This phase also includes completing the shop wing corridor, finalizing the vestibule, and installing associated canopies.
Throughout every phase, Finn Way emphasized rigorous adherence to safety protocols, proactive communication with stakeholders, and the execution of a meticulously planned schedule. This approach ensures the project is delivered efficiently while maintaining the highest standards of quality and minimizing disruptions to students, staff, and school operations.
The project also included the integration of an EarlyON Childcare and Family Center, along with the installation of new site services and a storm drain system, ensuring the school meets modern functionality and accessibility standards.