Finn Way provided general contracting services for the construction of a new water treatment plant and associated infrastructure, as well as the demolition of the existing water pumphouse in Gull Bay, Ontario.

The project improved water quality and system reliability for the community, incorporating modern treatment technologies and expanding the water distribution network.

Scope of Work

  • Installation of a raw water intake pipe extending into Lake Nipigon to source untreated water.
  • Construction of a low lift pumping station, including:
    • 2,400 mm diameter precast reinforced concrete wet well to collect raw water.
    • Raw water pumps for initial water transfer.
    • Pump house building to accommodate process piping, electrical controls, and mechanical components.
  • Installation of approximately 1,300 meters of new watermain to extend the distribution network.